Compute earthwork volume between two cross-sections using the average-end-area method: the average of the two end areas times the distance between them. Returns cubic feet, cubic yards (bank), and loose cubic yards after a swell/bulking allowance for hauling.

Try it now

Worked example

Volume: 7,500 cu ft · Bank volume: 277.777778 cu yd · Loose (haul) volume: 347.222222 cu yd

Inputs

Frequently asked

What is the average-end-area method?

Volume = ((Area A + Area B) ÷ 2) × distance. It's the standard quick method for earthwork between two measured cross-sections.

Why loose vs bank yards?

Excavated soil bulks up ('swell'), so you haul more loose volume than the in-ground (bank) volume. The swell % converts bank yards to loose yards.