Compute earthwork volume between two cross-sections using the average-end-area method: the average of the two end areas times the distance between them. Returns cubic feet, cubic yards (bank), and loose cubic yards after a swell/bulking allowance for hauling.
Try it now
Worked example
Volume: 7,500 cu ft · Bank volume: 277.777778 cu yd · Loose (haul) volume: 347.222222 cu yd
Inputs
- Cross-section area A (sq ft)
120 - Cross-section area B (sq ft)
180 - Distance between (ft)
50 - Swell / bulking %
25
Frequently asked
What is the average-end-area method?
Volume = ((Area A + Area B) ÷ 2) × distance. It's the standard quick method for earthwork between two measured cross-sections.
Why loose vs bank yards?
Excavated soil bulks up ('swell'), so you haul more loose volume than the in-ground (bank) volume. The swell % converts bank yards to loose yards.